1.When what is visible to
end-users is a deviation from the specified or expected behavoir,this is called:
a) an error
b) a fault
c) a failure
d) a defect
e) a mistake
2.Regression testing should
be performed
v- every week
w- after software has changed
x- as often as possible
y- when the environment has
changed
z- when the project manager
says
a) v&w are true, x&z
are false
b) w,x&y are true,v&z
are false
c) w&y are true,v,x &
z are false
d) w is true,v,x,y and z are
false
e) All of the above are true
3.IEEE829 test plan documentation
standard contains all of the following except:
a) test items
b) test deliverables
c) test task
d) test environment
e) test specification
4.Testing shoud be stopped
when:
a) all the planned test have
been run
b) time has run out
c) all faults have been fixed
correctly
d) both a) and c)
e) it depends on the risk
for the system being tested
5.Order numbers on a stock
contol system can range between 10000 and 99999 inclusive.Which of the following inputs might be a result of designing tests
for only valid equivalence classes and valid boundries?
a) 1000,50000,99999
b) 9999,50000,100000
c) 10000,50000,99999
d) 10000,99999
e) 9999,10000,50000,99999,100000
6.Consider the following statements
about early test design:
v- early test design can prevent
fault multiplication
w- faults found during early
test design are more expensive to fix
x- early test design can find
faults
y- early test design can cause
changes to the requirements
z- early test design takes
more effort
a) v,x&y are true,w&z
are false
b) x is true,v,w,y&z are
false
c) x & y are true,v,w&z
are false
d) v,x,y&z are true,w
is false
e) v&x are true,w,y &z
are false
7. Non Functional system testing
include:
a) testing to see where the
system does not function correctly
b) testing quality attributes
of the system including performance and usability
c) gaining user approval for
the system
d) testing a system feature
using only the software required for that function
e) testing for functions that
should not exist
8.Which of the following is
not part of configuration management:
a) status accounting of configuration
items
b) auditing conformance to
ISO 9000
c) identification of test
versions
d) record of changes to documentation
over time
e) controlled library access
9.Which of the following is
the main purpose of the integration strategy for integration testing in the small:
a) to ensure that all of the
small modules are tested adequately
b) to ensure that system interfaces
to other systems and networks
c) to specify which modules
to combine when,and how many at once
d) to ensure that the integration
testing can be performed by a small team
e) to specify how the software
should be divided into modules
10.What is the purpose of
test completion criteria in a test plan?
a) to know when a specific
test has finished its execution
b) to ensure that the test
case specification is complete
c) to set the criteria used
in generating test inputs
d) to know when testing planning
is complete
e) to plan when to stop testing